(Notice of bid extension) Southern Vietnam Power Projects Management Board (SPMB): Supply and transportation of 500kV auto-transformer

Southern Vietnam Power Projects Management Board (SPMB) published Invitation to bid on Vietnam Public Procurement Review issue No. 09 dated 14 January 2020 with the following contents:
 

Procurement package: Package 5: Supply and transportation of 500kV auto-transformer “Notice ref No.: 20200124844 - 00. Date of publication: 10/01/2020 15:13".

Project name: Upgrading power of 500kV Vinh Tan substation from 2x600MVA to 2x900MVA

Time of issuing bidding documents: from 09:00 am, 16 January 2020 to 09:00 am, 04 March 2020 (during office hours)

Bid closing time: 09:00 am, 04 March 2020

Now we would like to change:

Time of issuing bidding documents: before 09:00 am, 23 March 2020 (during office hours)

Bid closing time: 09:00 am, 23 March 2020

Bid opening time: 09:00 am, 23 March 2020.

Other information remains unchanged.