Procuring agency: Southern Vietnam Power Projects Management Board – Branch of National Power Transmission Corporation

Name of procurement: Supply and transportation of insulator & fittings, opgw & fittings for connection line. (Notice ref No IB2300117024 - 00. Date of publication: 05/6/2023 16:32)

- Implementation period: 240 days

Project name: 220kV Long Khanh Substation and Connection Lines.

Source of fund: National Power Transmission Corporation

Method of bidder selection: International open bidding, one-stage two envelope bidding

Time of issuing bidding documents: from 04:32 pm, 05 June 2023 to 09:00 am, 17 July 2023 (during office hours)

Place of issuing bidding documents: muasamcong.mpi.gov.vn

Price of bidding documents: VND 4,700,000

Bid security: VND 1,319,527,000 through banks or branches which legally operate in Viet Nam

Bid closing time: 09:00 am, 17 July 2023

Bid opening time: 09:15 am, 17 July 2023.