Southern Vietnam Power Projects Management Board – Branch of National Power Transmission Corporation published the extention of the Invitation to bid on Vietnam Public Procurement Review issue No. 133 dated 18 July 2023 with the following contents:

Procurement package: Package 10: Supply and transportation of insulator & fittings, opgw & fittings for connection line (Notice ref No. IB2300129355 - 00. Date of publication: 15/06/2023 16:21)

Project name: 220kV Nhon Trach 3 Power Plant – 500Kv Long Thanh Substation Transmission Line

Time of issuing bidding documents: from 04:21 pm, 15 June 2023 to 09:00 am, 07 August 2023 (during office hours)

Bid closing time: 09:00 am, 07 August 2023

Now we would like to change:

Time of issuing bidding documents: before 09:00 am, 07 September 2023 (during office hours)

Bid opening time: 09:15 am, 07 September 2023