Procuring agency: Department of Planning and Investment of Khanh Hoa province

Project name: The Cam Ranh Bay Urban Area project “Notice ref No PR2300016537 - 00. Date of publication: 25/04/2023 10:02"

Investment objectives: Technical infrastructure system; residential areas (commercial housing, social housing – resettlement); public works, services for residential and urban units (schools, health stations, markets, commercial centers...); system of parks and urban trees; resort service works, golf courses, theme parks. Contributing to putting the regional land fund into effective exploitation, promotion of socio-economic development in Cam Ranh Bay, Cam Ranh City.

Project scale: Land use scale: 1,254.14 ha; - The population size is about 230,779 people, with the number of houses including: + Commercial houses : (1) Semi-detached houses about 8,474 units, (2) Villas about 10,732 units; + Social houses: about 19,816 units (social housing, apartments about 18,450 units; adjacent social housing about 1,366 units). - Expected scale of construction architecture: Comply with the detailed planning scale of 1/500 of the project approved by the competent State agency

Project implementation progress: Project operation period: 50 years from the date the investor is allowed to decide on land allocation or land lease. - Project implementation progress: 05 years (from 2023 to the end of 2027)

Project location: Cam Loi Ward, Cam Ranh City, Khanh Hoa province; Cam Thinh Dong Ward, Cam Ranh City, Khanh Hoa province; Ba Ngoi Ward, Cam Ranh City, Khanh Hoa province; Cam Thuan Ward, Cam Ranh City, Khanh Hoa province; Cam Nghia Ward, Cam Ranh City, Khanh Hoa province; Cam Phuc Nam Ward + Cam Phu Ward + Cam Linh Ward + Cam Lap Ward + Cam Phuc Bắc Ward, Cam Ranh City, Khanh Hoa province

Land area: About 1,254.14 ha.

Land use period: -

Land use's purpose: The land use purpose of the Cam Ranh Bay Coastal Urban Area Project is determined according to the zoning plan scale 1/2000 of the project, including the main land-use functional subdivisions such as: + Land for tourism development. + Land for urban development. + Mixed and combined services land + Public land, social infrastructure, technical infrastructure ... - The specific land use purpose of each land plot under the Project will be determined according to the detailed plan scale 1/500 of the Project approved by a competent State agency.

Current status of the land area: The water surface of Cam Ranh Bay, Thuy trieu Lagoon, There are some households living on the land. Concretely : *Zone 1: Current status of residential and public works: The area has 202 housing buildings including solid and temporary houses, of which: Solid, semi-solid and stable house : 64 units; The remaining temporary houses are mostly camps of shrimp ponds; Low residential land area, accounting for 0.83% of the whole area. *Zone 2: Current status of residential and public works: The area with residential land area accounts for 0.75% of the whole area; Including 98 solid, semi-permanent and temporary housing buildings, of which: Solid, semi-permanent and stable housing is 44 units; The remaining temporary houses are mostly camps of shrimp ponds. *Zone 3: Current population status: Low residential land area accounts for 2.57% of the whole area; The current building has 130 houses including permanent, semi-permanent and temporary houses: Permanent and semi-permanent housing

Preliminary total project implementation cost: VND 85.293.883.000.000

Compensation, support and resettlement expense: VND 997.295.493.000

Deadline for investors to submit their project implementation registration document:25/05/2023 17:00

Address, phone number, fax number of the Department of Planning and Investment: Department of Planning and Investment of Khanh Hòa province, No 01 Tran Phu road, Xuong Huan ward, Nha Trang city, Khanh Hòa province. Phone number: 02583822906