Investment objectives: Building a modern new urban area, synchronous in technical and social infrastructure, creating a civilized urban landscape environment, realizing the approved zoning plan and contributing to perfecting the urban infrastructure, developing Dien Khanh district into a town. Creating a land fund with synchronous technical infrastructure to arrange for mass organizations and state administrative agencies according to the approved zoning planning; Providing a full range of functions of the complete urban area to meet the needs of living, working and entertainment for local people
Project scale: According to Clause 4, Article 1 of Decision No. 2657/QD-UBND dated November 6, 2023 of Khanh Hoa Provincial People's Committee regarding Approval of Investment Policy of Dien Khanh District Administrative Urban Area Project.
Summary of basic requirements of the project: -
Project implementation progress: Project operation period: 50 years from the date the Provincial People's Committee issues the Decision approving the investment policy. - Project implementation progress: 06 years from the date the Provincial People's Committee issues the decision on investor selection, expected from the first quarter of 2024 to the fourth quarter of 2029
Project investment location: Dien Thanh Ward, Dien Khanh District, Khanh Hoa Province
Land area: 89.1 ha
Land use purposes: New urban area with main land use functions such as: agency land; public works land; residential land: low-rise residential land (adjacent buildings, villas), high-rise mixed land; green land on water surface – Sports center; traffic land.
Approved planning criteria: Determined according to the detailed plan (scale 1/500) approved by a competent authority, ensuring conformity with the zoning plan (scale 1/2000) Dien Khanh district administrative urban area approved by the People's Committee of Dien Khanh district in Decision No. 4431/QD-UBND dated 31/12/2014, approving local adjustments to the planning in Decision No. 1604/QD-UBND dated 12/07/2018 and Decision No. 663/QD-UBND dated 25/03/2022
Current status of the land area: The project land has not been cleared, with the current status of land use as follows: 1. Land for other annual crops. Land type code: BHK; HNK; NHK; DM. Area (ha): 4,48. Rate (%): 5,03% 2. Soil for perennial plants. Land type code: CLN; TRE. Area (ha): 0,35. Rate (%): 0,39% 3. Traffic land + irrigation land. Land type code: DGT+DTL. Area (ha): 6,74. Rate (%): 7,56% 4. Land for rice cultivation. Land type code: LUC; 1L; 2L.Area (ha): 74,38. Rate (%): 83,48% 5. Land in the countryside; Land in rural areas and land for perennial crops; Rural land and rice land. Land type code: ONT; ONT+CLN; ONT+LUC. Area (ha): 1,48. Rate (%): 1,66% 6. Land managed by the Commune People's Committee. Land type code: UB (Hg; CD; X.CD; ND). Area (ha): 1,67. Rate (%): 1,87% Total: 89,1 ha. Rate (%): 100,00%
Preliminary total project implementation cost: VND 1.765.673.312.000
Compensation, support and resettlement expense: VND 246.330.373.000
Deadline for investors to submit their project implementation registration document:08/02/2024 17:00
Address, phone number, fax number of the Department of Planning and Investment: Department of Planning and Investment of Khanh Hoa province, No 01 Tran Phu road, Xuong Huan ward, Nha Trang City, Khanh Hoa province. Phone number: 02583822906; Fax: 02583.822.906