Investment objectives: Building a synchronous and modern urban area to, ensure the standard requirements of environmental sanitation, security, traffic safety, fire prevention, urban landscape, civilization, harmonious connection with surrounding areas. - Concretize detailed construction planning of 1/500 scale approved by the Provincial People's Committee under the Decision No. 825/QD-UBND dated March 30, 2021
Project scale: a) Tổng diện tích: 109.438,9 m2. b) Population size: 1.200 people. c) Construction scale: - Commercial and service zones, land use area 1,963.10 m2, 03 floors high; - Low-rise housing, land use area 40,618.2 m2 (area of land plots from 117.0 m2 to 230.0 m2), 315 units, 04 floors high; - Trees, sports, landscape, square: total land use area is 9,824.9 m2, comprise: sports green land area 5,831.80m2, 01 floors high; square land area 1,907.70 m2; green land area, landscape 2,085.40 m2; - House of culture has a land area of 990.20 m2, 02 floors high; - The preschool has a land area of 2,041.70 m2, 02 floors high; - The wastewater treatment plant has a land area of 386.40m2, 01 floors high; - Technical infrastructure system: Invest in synchronous construction of technical infrastructure systems according to the detailed planning of 1/500 scale approved by the Provincial People's Committee in the Decision No. 825/QD-UBND dated March 30, 2021, and current building codes and standards, including: Leveling the ground; traffic, parking lot, urban lighting, water supply system, storm water drainage system, sewage drainage system, electrical and communication system, transformer station, fire protection. d) Compensation for ground clearance. e) Handling of public properties - Land for irrigation and traffic (including: 600 m long concrete road, road bed width 7.0 m, 3.5 m wide road surface; 493.76 m long asphalt road, road bed width 7.0 m; 300.0 m long asphalt road, road bed width 5.0 m; 493.76 m long domestic drainage ditch, 1 m . wide, 1 m . high) - Land for cultural houses block 2A: Keep houses and land intact for people to live in the community; Investors invest in renovating, upgrading or building new cultural houses of equivalent (or better) size and standards, in accordance with the approved planning, then hand it over to the locality for management and use.The investment value of these assets is included in the investment capital of the project, but are not reimbursed.
Project implementation progress: Project implementation duration: No more than 50 years according to the provisions of the law on investment. - Project implementation progress: Complete the project within 04 years from the date of eligibility to start construction as prescribed by law
Project location: Thanh Chuong town, Thanh Chuong district, Nghe An province
Land area: 109.438,9 m2
Land use period: -
Land use's purpose: -
Current status of the land area: 1.2.11 Actual status of the land area: No. Type of land Area (m2) 1 Land for traffic (DGT) 13,791.07 2 Land for the construction of cultural houses (DVH) 930.57 3 Land for irrigation (DTL) 1,918.40 4 Land for aquaculture (NTS) 1,646.19 5 Residential land (ONT) 170.12 6 Land area for rice cultivation (LUC) 84,592.54 7 Available plain (BSC) 931.70 8 Colored soil (BHK) 132.93 9 Soil for perennial plants (CLN) 425.43 10 Land for building a working headquarters 4,900.00 Total 109,438.95 (Exact parameters of the origin and current status of land use will be surveyed and reported in detail in the next steps when extracting for measurements and extract of project land area)
Preliminary total project implementation cost: VND 889.266.000.000
Compensation, support and resettlement expense: VND 20.900.000.000
Deadline for investors to submit their project implementation registration document:17/05/2023 08:00
Address, phone number, fax number of the Department of Planning and Investment: Department of Planning and Investment of Nghe An province, No 20 Truong Thi road, Truong Thi ward, Vinh city, Nghe An province. Phone number: 0383844636