Project's investment objectives: Forming a new urban area with synchronous technical and social infrastructure, ensuring connection with the current residential area; meet the demand for housing in the condition that the city is in the process of strong urbanization; contribute to increase revenue for the local budget.
Scale of the project investment: Estimated population size is about 4,485 people; Invest in building technical and social infrastructure systems of Liem Tiet new urban area in Liem Tiet commune, Phu Ly city according to the approved detailed construction planning of 1/500 scale. In particular: Technical infrastructure projects; Social infrastructure works; Trade and service centers; Housing works.
Preliminary total project implementation cost: VND 2.434.145.100.000
Compensation, support and resettlement expense: VND 103.928.600.000
Summary of the basic requirements of the project: Invest in building a system of technical and social infrastructure in the urban area, ensuring compliance with the approved 1/500 detailed planning and approved investment policy, ensuring synchronous connectivity with technical infrastructure in surrounding areas; updating and synchronously connecting with technical infrastructure of projects that have been and are being implemented in the region.
Investment duration and schedule: Project implementation schedule: 2022 - 2026. Project operating time: 50 years (from the date of issuance of the Investor Approval Decision)
Project location: Liem Tiet commune, Phu Ly city, Ha Nam province.
Land area: About 42.3ha
Land use's purpose: Including residential land, urban public land, public land for residential units, green land, land for education, land for technical infrastructure, land for parking, land for traffic
Approved planning criteria: Land use structure: 422,986.5 m2, including: New residential land (residential land Adjacent to street, Adjacent, Villa, Social housing, Resettlement) 168,414.8 m2; Urban land for public works (commercial and service land) 17,621.7 m2; Land for public works at residential unit level (land for medical stations, land for cultural houses) 3,198.0 m2; Land for greenery (urban trees, green trees for residential units) 28,858.4 m2; Education land (kindergarten) 2,803.1 m2; Technical infrastructure land 1,599,6 m2; Parking lot land 1,497.9 m2; Traffic land 198,993.0 m2. The norms of spatial organization of landscape architecture and urban design; technical infrastructure system planning: comply with the provisions of the Decision approving the planning
Deadline for investors to submit their project implementation registration document: 22/06/2022 09:00
Address, phone number, fax number of the Department of Planning and Investment: Ha Nam Department of Planning and Investment, No. 15, Tran Phu Street, Quang Trung Ward, Phu Ly City, Ha Nam Province. Phone: 0226.3852.701; Fax: 0226.3852.701
Other information: According to the decision approving the planning and the decision approving the investment policy of the People's Committee of Ha Nam province.