- Implementation period: 150 days
Project name: Block 09.1
Source of fund: The source of funding for implementation of the bidding package is Vietsovpetro’s financial plan for production activities in 2023
Method of bidder selection: International open bidding, one-stage one envelope bidding
Time of issuing bidding documents: from 03:26 pm, 07 June 2023 to 09:00 am, 18 July 2023 (during office hours)
Place of issuing bidding documents: muasamcong.mpi.gov.vn
Price of bidding documents: VND 500,000
Bid security: VND 91,200,000 or USD 3,800 through banks or branches which legally operate in Viet Nam
Bid closing time: 09:00 am, 18 July 2023
Bid opening time: 09:30 am, 18 July 2023.