- Implementation period: 135 days
Project name: Instrument & Electrical bulk materials Package For Expansion of Gaslift and Manifold system on BK14/BT7 2nd stage Project – Block 09-1 (bidding package No. VT-3909/23-XL-DA-TLAT)
Source of fund: The source of funding for implementation of the bidding package is Vietsovpetro’s financial plan for production activities in 2023
Method of bidder selection: International open bidding, one-stage one envelope bidding
Time of issuing bidding documents: from 02:45 pm, 24 November 2023 to 09:00 am, 03 January 2024 (during office hours)
Place of issuing bidding documents: muasamcong.mpi.gov.vn
Price of bidding documents: VND 500,000
Bid security: VND 63,000,000 or USD 2,650 through banks or branches which legally operate in Viet Nam
Bid closing time: 09:00 am, 03 January 2024
Bid opening time: 09:30 am, 03 January 2024.