Name of the procuring entity: Board of transport construction investment project of Phu Tho province
Brief description of the project:
- Project name: The route from Dong Quang Bridge to National Road.32 at Viet Tien T-junction, Dich Qua Commune, Thanh Son District in the form of BOT contract “http://muasamcong.mpi.gov.vn. Notice ref No.: 20200324273 - 01. Date of publication: 11/03/2020 14:13”
- Projected site: Thanh Thuy district and Thanh Son district, Phu Tho province.
- Projected implementation period: Completed before December 31, 2021
- Estimated total investment capital: VND 1.284.696.611.000
- Project objectives: Invest in building roads to create new corridors, increase connectivity to develop industry, handicrafts, tourism and services in Thanh Thuy, Thanh Son and Tan Son districts and other districts in the region; support and maximize the effectiveness of the construction of Dong Quang Bridge across the Da River connecting Hanoi capital with Phu Tho, Hoa Binh, Son La and Yen Bai province through National Road.32 and National Road.70B, creating axis connecting with Noi Bai - Lao Cai highway through intersections IC-10, IC-11; at the same time, contributing to gradually complete the modern transport infrastructure in the direction from Hanoi to Xuan Son National Park and vice versa, making tourism become a key economic sector of Tan Son district.
- Project modules: For main routes: Constructing new route with a total length of 24,695 km, a design speed of 80 km/h; starting point of the route (km0) at the T - junction of Dong Quang bridge and ĐT.317 at km10+420, of Dong Luan commune, Thanh Thuy district; the end point (km24+695.73) intersects with National Road.32 at Viet Tien T-junction, at Dich Qua commune, Thanh Son district; - For branch routes: Constructing the route connecting the main route with the National Road.70B with a length of 318.59m, a design speed of 60 km/h. The starting point of the route (km0) at km17+916.08 of the main route (in Thuc Luyen commune, Thanh Son district); The end point (km0+318.59) intersects with National Road.70B in Thuc Luyen commune, Thanh Son district.
- Type contract: BOT
- State funding for project (if any): -
Selection method: international open bidding with prequalification
Time of issuing prequalification document: from 01:13 pm, 11 March 2020 to 9:00 am, 27 April 2020 (during office hours)
Place of issuing prequalification document: Board of transport construction investment project of Phu Tho province; Address: No. 1508, Hung Vuong street, Gia Cam ward, Viet Tri city, Phu Tho province
Price of prequalification document: VND 10,000,000
Bid closing time: 9:00 am, 27 April 2020
Bid opening time: 9:30 am, 27 April 2020.