Project name: Social housing area in Ngan Hang Hill Residential Area, Hong Hai Ward and Cao Thang Ward, Ha Long City, Quang Ninh Province (No. of: 20220351293 - 00. Date of publication: 15 giờ 10 ngày 21/03/2022)

Project's investment objectives: Addressing the needs of social housing for the subjects as prescribed in Article 49 of the Law on Housing 2014; Concretize the detailed construction planning project of 1/500 scale of the social housing area in the residential area of Ngan Hang hill, Hong Hai ward and Cao Thang ward, Ha Long city, which has been approved by the People's Committee of Ha Long city. at Decision No. 9423/QD-UBND dated October 21, 2021, Contributing to embellishing urban architecture, completing the landscape environment in the direction of modern civilization.

Scale of the project investment: Total land use area of the project is 25.900 m2, of which: Construction land area 12.835,5 m2, green land 4.172,2 m2, technical infrastructure land 8.892,3 m2; Estimated population size: About 3.880 people.

Preliminary total project implementation cost: VND 1.361.000.000.000

Compensation, support and resettlement expense: None

Summary of the basic requirements of the project: - Invest in building the technical infrastructure system within the project area of 25.900m2 and connect the general technical infrastructure of Ngan Hang Hill Residential Area project. - Investment in construction of 03 apartment buildings, of which: 02 high-rise buildings with 19 floors + 01 mezzanine + 01 technical floor; 01 17-storey building + 01 mezzanine floor + 01 technical floor + 01 semi-basement floor; construction area 7.409,7 m2; total construction floor area is about 125.220,3 m2.

Investment duration and schedule: (i) Organizing investor selection, completing investment preparation procedures: From Quarter IV/2021 to Quarter IV/2022; (ii) Construction work: Quarter I/2023 to Quarter IV/2025; (iii) Completing the entire project, handing over and putting into use: In the first quarter of 2026.

Project location: At Ngan Hang Hill Residential Project, Hong Hai Ward and Cao Thang Ward, Ha Long City.

Land area: Approximately 25.900 m2.

Land use's purpose: Implementing the project of social housing area in Ngan Hang Hill residential area, Hong Hai ward and Cao Thang ward, Ha Long city.

Approved planning criteria: 12.835,5 m2 of construction land, 172,2 m2 of green tree land, 8.892,3 m2 of technical infrastructure land.

Deadline for investors to submit their project implementation registration document: 25/04/2022 16:30

Address, phone number, fax number of the Department of Planning and Investment: Department of Planning and Investment of Quang Ninh Province, 5th floor, Inter-agency headquarters No. 2, Hong Ha ward, Ha Long city, Quang Ninh province. Phone number: 0203.3835687. Email: skhvdt@quangninh.gov.vn.

Other information: Clean government managed land