- Implementation period: 180 days
Project name: Construction of overhaul items in 2023, phase 5
Source of fund: fund for overhaul of EVNNPT
Method of bidder selection: International open bidding, one-stage two envelope bidding
Time of issuing bidding documents: from 07:47 am, 15 November 2023 to 10:00 am, 26 December 2023 (during office hours)
Place of issuing bidding documents: muasamcong.mpi.gov.vn
Price of bidding documents: Free
Bid security: VND 395,000,000 through banks or branches which legally operate in Viet Nam
Bid closing time: 10:00 am, 26 December 2023
Bid opening time: 10:00 am, 26 December 2023.