- Implementation period: 460 days
Project name: Upgrade of the plant control system (DCS)- Uong Bi Thermal Power Plant Project
Source of fund: EVNGENCO1’s construction investment
Method of bidder selection: International open bidding, one-stage two envelope bidding
Time of issuing bidding documents: from 10:51 am, 15 February 2023 to 09:00 am, 18 April 2023 (during office hours)
Place of issuing bidding documents: muasamcong.mpi.gov.vn
Price of bidding documents: VND 2,000,000
Bid security: VND 3,200,000,000 or USD 135,500 through banks or branches which legally operate in Viet Nam
Bid closing time: 09:00 am, 18 April 2023