Central Power Projects Management Board (CPMB): Supply and transportation of primary equipment and materials, insulators, OPGW and accessories

0:00 / 0:00
0:00
Central Power Projects Management Board (CPMB) issued on December 1, 2021 its notice of its notice of bid invitation for procurement package of Supply and transportation of primary equipment and materials, insulators, OPGW and accessories with details as follows:

Procuring agency: Central Power Projects Management Board (CPMB)

Name of procurement package: Package No.11: Supply and transportation of primary equipment and materials, insulators, OPGW and accessories “Notice ref No 20211202492 - 00. Date of publication: 01/12/2021 14:56"

- Implementation period: 210 days

Project name: 220kV Ninh Phuoc substation – 500kV Thuan Nam substation double transmission line

Source of fund: EVNNPT

Method of bidder selection: International open bidding, one-stage two envelope bidding

Time of issuing bidding documents: from 02:56 pm, 01 December 2021 to 09:00 am, 14 January 2022 (during office hours)

Place of issuing bidding documents: muasamcong.mpi.gov.vn

Price of bidding documents: VND 4,600,000 or USD 200

Bid security: VND 567,000,000 or USD 25,000 through banks or branches which legally operate in Viet Nam

Bid closing time: 09:00 am, 14 January 2022

Bid opening time: 09:00 am, 14 January 2022.