Procuring agency: Central Power Projects Management Board (CPMB)
Name of procurement package: Package No.6: Supply and transportation 500kV Shunt Reactor “Notice ref No 20211055542 - 00. Date of publication: 20/10/2021 09:54"
- Implementation period: 300 days
Project name: 500kV transission line connecting 500kV Thuan Nam substation to 500kV Van Phong TPP – Vinh Tan TPP transmission line
Source of fund: EVNNPT
Method of bidder selection: International open bidding, one-stage two envelope bidding
Time of issuing bidding documents: from 09:54 am, 20 October 2021 to 09:00 am, 01 December 2021 (during office hours)
Place of issuing bidding documents: muasamcong.mpi.gov.vn
Price of bidding documents: VND 7,200,000
Bid security: VND 2,100,000,000 or USD 95,000 through banks or branches which legally operate in Viet Nam
Bid closing time: 09:00 am, 01 December 2021
Bid opening time: 09:00 am, 01 December 2021.