(Notice of bid extension) CPMB: Supply and transportation 500kV Shunt Reactor

0:00 / 0:00
0:00
Central Power Projects Management Board (CPMB) published Invitation to bid on Vietnam Public Procurement Review issue No.246 dated 27 December 2021 with the following contents:

Procurement package: Package No.6: Supply and transportation 500kV Shunt Reactor “Notice ref No 20211055542 - 00. Date of publication: 20/10/2021 09:54"

Project name: 500kV transission line connecting 500kV Thuan Nam substation to 500kV Van Phong TPP – Vinh Tan TPP transmission line

Time of issuing bidding documents: from 09:54 am, 20 October 2021 to 09:00 am, 11 January 2022 (during office hours)

Bid closing time: 09:00 am, 11 January 2022.

Now we would like to extend:

Time of issuing bidding documents: before 09:00 am, 25 January 2022 (during office hours)

Bid opening time: 09:00 am, 25 January 2022

Other information remains unchanged.