Procurement package: Package No. 1TB-HB "Supply of Electro-Mechanical Equipment” “Notice ref No 20210228651 - 00. Date of publication: 22/02/2021 15:01"
Project name: Hoa Binh Hydropower Plant Extension Project
Time of issuing bidding documents: from 03:01 pm, 22 February 2021 to 09:30 am, 22 April 2021 (during office hours)
Bid closing time: 10:00 am, 22 April 2021.
Now we would like to extend:
Time of issuing bidding documents: before 02:00 pm, 12 May 2021 (during office hours)
Bid opening time: 02:30 pm, 12 May 2021
Other information remains unchanged.