(Notice of bid extension) SPMB: Supply and transportation of 500kV auto-transformer

0:00 / 0:00
0:00
The Southern Vietnam Power Projects Management Board (SPMB) published Invitation to bid on Vietnam Public Procurement Review issue No.166 dated 01 September 2020 with the following contents:

Procurement package: Package 5: Supply and transportation of 500kV auto-transformer “Notice ref No 20200720107 - 00. Date of publication: 08/07/2020 09:35"

Project name: Power enhancement for 500kV Nha Be and O Mon Substations (Power transformer no.2)

Time of issuing bidding documents: from 09:35 am, 08 July 2020 to 09:00 am, 11 September 2020 (during office hours)

Bid opening time: 09:15 am, 11 September 2020.

Now we would like to extend:

Time of issuing bidding documents: before 09:00 am, 18 September 2020 (during office hours)

Bid opening time: 09:15 am, 18 September 2020

Other information remains unchanged