Procuring agency: Southern Vietnam Power Projects Management Board – Branch of National Power Transmission Corporation (SPMB)

0:00 / 0:00
0:00
Name of procurement package: Package No. 14: Supply and Transportation of Primary Equipment and Materials for Substation (Notice ref No.: 20220507587 - 00. Date of publication: 05/05/2022 16:10)

- Implementation period: 240 days

Project name: 220kV Vinh Chau substation and connection lines

Source of fund: SPMB

Method of bidder selection: International open bidding, one-stage two envelope bidding

Time of issuing bidding documents: from 04:10 pm, 05 May 2022 to 09:00 am, 15 June 2022 (during office hours)

Place of issuing bidding documents: muasamcong.mpi.gov.vn

Price of bidding documents: VND 4,700,000 or USD 200

Bid security: VND 788,940,000 or USD 34,227 through banks or branches which legally operate in Viet Nam

Bid closing time: 09:00 am, 15 June 2022

Bid opening time: 09:15 am, 15 June 2022