- Implementation period: 180 days
Project name: Installation of 220kV Auto-transformer at 220kV Vinh Tuong Substation
Source of fund: National Power Transmission Corporation (EVNNPT)
Method of bidder selection: International open bidding, one-stage two envelope bidding
Time of issuing bidding documents: from 10:59 am, 24 February 2023 to 02:00 pm, 06 April 2023 (during office hours)
Place of issuing bidding documents: muasamcong.mpi.gov.vn
Price of bidding documents: VND 4,700,000
Bid security: VND 794,000,000 or USD 33,000 through banks or branches which legally operate in Viet Nam
Bid closing time: 02:00 pm, 06 April 2023
Bid opening time: 02:30 pm, 06 April 2023.