Project name: Hai Van New Urban Area, Ben Sung town, Nhu Thanh district, Thanh Hoa province

0:00 / 0:00
0:00
Department of Planning and Investment of Thanh Hoa Province issued on October 7, 2021 its notice of its notice of bid invitation for project of Hai Van New Urban Area, Ben Sung town, Nhu Thanh district, Thanh Hoa province with details as follows:

Procuring agency: Department of Planning and Investment of Thanh Hoa Province

Project name: Hai Van New Urban Area, Ben Sung town, Nhu Thanh district, Thanh Hoa province “Notice ref No 20211017989 - 00. Date of publication: 07/10/2021 14:01"

Project's investment objectives: Concretizing the approved detailed planning; forming new living quarters, aiming to meet the needs of residential houses, serve the lives and living activities of local people, contributing to embellish the urban landscape; mobilizing investment capital from economic institutions to implement site clearance and infrastructure construction; contributing to the local socio-economic development

Scale of the project investment: a) Construction scale: Completely investing in the synchronous construction works according to the detailed planning approved by Chairman of the People's Committee of Nhu Thanh District under Decision No. 2056/QĐ UBND dated May 22, 2020 and amended under Decision No. 1353/QĐ-UBND dated June 10, 2021, including the following works items: - Completely investing in the technical infrastructure works (for an area of about 14.6ha, consisting of leveling, traffic, water supply - drainage, electricity supply, lighting, green parks, parking lots, wastewater treatment stations etc.) and cultural house. - Investing in the rough part and finishing the facade of townhouses (marked from LK-1 to LK-15) and villas (marked from BT-1 to BT-3) and completely investing in the commercial and service works (marked TM-DV), preschool (marked TH:MN). b) Preliminary structure of housing products: 372 townhouses; 66 villas. c) Population size: About 2,000. d) Land fund for social housing development: None

Preliminary total project implementation cost: VND 913.438.000.000

Compensation, support and resettlement expense: VND 27.258.000.000

Summary of the basic requirements of the project: Completely investing in the technical infrastructure works (for an area of about 14.6ha, consisting of leveling, traffic, water supply - drainage, electricity supply, lighting, green parks, parking lots, wastewater treatment stations etc.) and cultural house. - Investing in the rough part and finishing the facade of townhouses (marked from LK-1 to LK-15) and villas (marked from BT-1 to BT-3) and completely investing in the commercial and service works (marked TM-DV), preschool (marked TH:MN)

Investment duration and schedule: 05 years (from the date of approving the investor selection results or investor approval)

Project location: Ben Sung town, Nhu Thanh district, Thanh Hoa province.

Land area: About 14.6ha (excluding 2.3ha of current residential land area and 0.36ha of area for traffic at land lots N5, N8 out of the 17.26ha total area according to the detailed planning approved)

Land use's purpose: According to the decision on land allocation or land lease issued by the competent authority

Approved planning criteria: According to the Decision No. 2056/QĐ-UBND dated May 22, 2020 and Decision No. 1353/QĐ-UBND dated June 10, 2021 of the Chairman of Nhu Thanh District People's Committee

Deadline for investors to submit their project implementation registration document:10/11/2021 09:00

Address, phone number, fax number of the Department of Planning and Investment: Department of Planning and Investment of Thanh Hoa Province. - Address: 45B Le Loi Avenue, Lam Son Ward, Thanh Hoa City, Thanh Hoa Province. Phone number: 02373854427; Fax: 02373851451

Other information: Current status of the land: The land area planned for the project is partly residential land and mainly agricultural production land. Land is allocated to households for management and use.