Central Power Projects Management Board (CPMB): Supply and transportation of primary equipment & materials and accessories

0:00 / 0:00
0:00
Central Power Projects Management Board (CPMB) issued on November 30, 2021 its notice of its notice of bid invitation for procurement package of Supply and transportation of primary equipment & materials and accessories with details as follows:

Procuring agency: Central Power Projects Management Board (CPMB)

Name of procurement package: Package No.7: Supply and transportation of primary equipment & materials and accessories “Notice ref No 20211111495 - 00. Date of publication: 30/11/2021 16:57"

- Implementation period: 240 days

Project name: Installation of the second transformer of 220kV Lang Son Substation

Source of fund: EVNNPT

Method of bidder selection: International open bidding, one-stage two envelope bidding

Time of issuing bidding documents: from 04:57 pm, 30 November 2021 to 09:00 am, 11 January 2022 (during office hours)

Place of issuing bidding documents: muasamcong.mpi.gov.vn

Price of bidding documents: VND 4,600,000 or USD 200

Bid security: VND 667,000,000 or USD 29,000 through banks or branches which legally operate in Viet Nam

Bid closing time: 09:00 am, 11 January 2022

Bid opening time: 09:00 am, 11 January 2022.