Procuring agency: Southern Vietnam Power Projects Management Board - Branch of National Power Transmission Corporation

0:00 / 0:00
0:00
Name of procurement: Package 11: Supply and transportation of Insulator & fittings, OPGW & fittings for transmission line (Notice ref IB2300389141 - 00. Date of publication: 28/12/2023 16:51)

- Implementation period: 240 days

Project name: The Second circuit of The 220kV Bao Loc - Song May transmission line

Source of fund: National Power Transmission Corporation

Method of bidder selection: International open bidding, one-stage two envelope bidding

Time of issuing bidding documents: from 04:51 pm, 28 December 2023 to 09:00 am, 19 February 2024 (during office hours)

Place of issuing bidding documents: muasamcong.mpi.gov.vn

Price of bidding documents: VND 4,700,000

Bid security: VND 2,156,072,000 through banks or branches which legally operate in Viet Nam

Bid closing time: 09:00 am, 19 February 2024