The Power Transmission projects management board issued on November 06, 2020 its notice of its notice of bid invitation for procurement package of Supply and transportation of 123kV-40MVAr Shunt with details as follows:

Procuring agency: The Power Transmission projects management board

Name of procurement package: Package No.03: Supply and transportation of 123kV-40MVAr Shunt “Notice ref No 20201117149 - 00. Date of publication: 06/11/2020 15:31"

- Implementation period: 240 days

Project name: High Voltage Limitting Solutionat 220kv Lao Cai Substations

Source of fund: EVNNPT

Method of bidder selection: International open bidding, one-stage two envelope bidding

Time of issuing bidding documents: from 03:31 pm, 06 November 2020 to 10:00 am, 17 December 2020 (during office hours)

Place of issuing bidding documents: muasamcong.mpi.gov.vn

Price of bidding documents: VND 4,500,000 or USD 200

Bid security: VND 1,700,000,000 or USD 73,000 through banks or branches which legally operate in Viet Nam

Bid closing time: 10:00 am, 17 December 2020